City of Coral Gables

File #: 22-4185    Version: 1 Name: Critical Path Svcs Contract Modification Re: Fink Studio
Type: Resolution Status: Adopted
File created: 5/20/2022 In control: City Commission
On agenda: 5/31/2022 Final action: 5/31/2022
Enactment date: 5/31/2022 Enactment #: 2022-137
Title: A Resolution of the City Commission authorizing modification to IFB 2020-024 H. George Fink Studio Restoration Project with Critical Path Services, Inc., pursuant to Section 2-764(b), Approval of Change Orders and Contract Modifications of the City’s Procurement Code in an estimated amount of $125,000 for additional work to be performed, as well as any other reasonable cost identified during the final delivery of this project not to exceed the available budget. Lobbyist: N/A
Attachments: 1. Signed Resolution 2022-137, 2. Critical Path Fink Studio Contract Modification COVER, 3. Critical Path Fink Studio Contract Modification RESOL, 4. Speaker Cards

Title

A Resolution of the City Commission authorizing modification to IFB 2020-024 H. George Fink Studio Restoration Project with Critical Path Services, Inc., pursuant to Section 2-764(b), Approval of Change Orders and Contract Modifications of the City’s Procurement Code in an estimated amount of $125,000 for additional work to be performed, as well as any other reasonable cost identified during the final delivery of this project not to exceed the available budget.

 

Lobbyist: N/A

 

 

Body

On October 13, 2020, the City Commission accepted the recommendation to award IFB Contract 2020-024 for the H. George Fink Studio Restoration Project to Critical Path Services, Inc., the lowest responsive and responsible bidder. 

 

The H. George Fink Studio was constructed in 1920 and is a local historic landmark. This contract modification request will address additional work to be incorporated into the project and is a result of unforeseen conditions, typical of a restoration project of this complexity.

 

The Public Works Department recommends approval of this request.