City of Coral Gables

File #: 17-6592    Version: 1 Name: UM 5827-5855 Ponce de Leon Blvd outside sewer conncection
Type: Resolution Status: Adopted
File created: 10/2/2017 In control: City Commission
On agenda: 10/10/2017 Final action: 10/10/2017
Enactment date: 10/10/2017 Enactment #: 2017-292
Title: A Resolution authorizing the execution of an agreement for sewer connection for property located outside the City’s sewer district at 5827 and 5855 Ponce de Leon Boulevard, Coral Gables, Florida to the City of Coral Gables wastewater collection / transmission system, subject to the requirements of the Public Works Department as provided under chapters 62 and 78 of the City Code, Ordinance No. 2007-29 and 2009-39 and Resolution No. 2008-07; and provided that the executed agreement be made part of this resolution.
Attachments: 1. Signed Resolution 2017-292, 2. UM Ponce Building outside sewer connection - COVER, 3. UM Ponce Building outside sewer connection - RESOL, 4. city code 78-106, 5. Ordinance 2007-29, 6. Ordinance No. 2009-39, 7. Resolution No. 2008-07
Title
A Resolution authorizing the execution of an agreement for sewer connection for property located outside the City’s sewer district at 5827 and 5855 Ponce de Leon Boulevard, Coral Gables, Florida to the City of Coral Gables wastewater collection / transmission system, subject to the requirements of the Public Works Department as provided under chapters 62 and 78 of the City Code, Ordinance No. 2007-29 and 2009-39 and Resolution No. 2008-07; and provided that the executed agreement be made part of this resolution.
Body
Cherokee Consulting, Inc., on behalf of the property Owner, University of Miami, is requesting authorization for an outside sewer connection to the City Sanitary sewer district to serve two (2) existing buildings; the buildings are located at 5827 and 5855 Ponce de Leon Boulevard, Coral Gables, Florida; and it shall be subject to the requirements of the Public Work Department, as set forth in Chapter 62 and 78 of the City Code, Ordinance No. 2007-29, and No. 2009-39 and Resolution No. 2008-07.

The properties are located outside City’s sewer service area and new private gravity system will be installed to serve the project. On July 7, 2017, the University of Miami entered into a Consent Agreement with Miami-Dade Department of Regulatory and Economic Resources (MDC-RER). The City of Coral Gables shall provide assurance that it will not issue a Certificate of Completion, Temporary Certificate of Occupancy, Certificate of Occupancy, Temporary Certificate of Use or Certificate of Use, or other municipal approvals granting occupancy or use of the establishment, prior to MDC-RER issuing a Sewer Extension permit and certifying the Sewer Extension.

Flows from the project will connect through the existing private gravity main owned and maintained by University of Miami, which is located along Levante Avenue west of Sagua Avenue. As per MDC-RER, the receiving Pump Station shall have sufficient capacity for the proposed project and all downstream pump ...