City of Coral Gables

File #: 15-4233    Version: 1 Name: Ric-Man negotiations for GMP for MM & Giralda
Type: Resolution Status: Adopted
File created: 8/24/2015 In control: City Commission
On agenda: 8/27/2015 Final action: 8/27/2015
Enactment date: 8/27/2015 Enactment #: 2015-206.1
Title: A Resolution authorizing the City Manager to begin negotiations with Ric-Man International, Inc. for a Guaranteed Maximum Price (GMP) for the construction of the Miracle Mile and Giralda Avenue Streetscape project.
Attachments: 1. RicMan negotiations for miracle mile const COVER, 2. RicMan negotiations for miracle mile const RESOL, 3. Verbatim Transcript - Special CCMtg August 27, 2015
Title
A Resolution authorizing the City Manager to begin negotiations with Ric-Man International, Inc. for a Guaranteed Maximum Price (GMP) for the construction of the Miracle Mile and Giralda Avenue Streetscape project.
Body
In December 2014, the City Commission approved the award of a design contract to Cooper Robertson for the Miracle Mile/Giralda Avenue Streetscape project. Since then, the design team through guidance and leadership provided by the City Commission, project Steering Committee, Boards and Committees, and Community Open Houses, has progressed the project from conceptual design through design development with broad community support.

The project includes the transformation of the public realm to create a civic promenade that will become a focal point for the region. When completed, Miracle Mile will include a beautiful pedestrian environment nearly 50% wider than it is today. This new environment will include extensive landscaping and trees, sidewalk cafes, public art, beautiful lighting, and comfortable and inviting street furnishings. Additionally, Giralda Avenue will be a spectacular shared pedestrian environment that includes creative and artful paving, lighting, and landscaping. It is anticipated that Miracle Mile and Giralda Avenue will be streets that are world renowned, and a “must place to be.”

On April 24th, 2015 the City Commission approved the selection of Ric-Man International, Inc. as the Construction Manager at Risk contractor for the project. Subsequently, staff executed a design services phase contract with Ric-Man International, Inc. As the project is entering the construction documents and permitting phase, it is time to begin negotiations with Ric-Man International, Inc. for a Guaranteed Maximum Price (GMP) to construct the project. The negotiations for the GMP will be based on the project as presented earlier during the workshop this date and specific guidance and direction provided by the City Commission during the ...

Click here for full text