File #: 25-9784    Version: 1 Name: Gavarrete Contract Mod - Lot 8-17 project
Type: Resolution Status: Adopted
File created: 9/16/2025 In control: City Commission
On agenda: 9/25/2025 Final action: 9/25/2025
Enactment date: 9/25/2025 Enactment #: 2025-368
Title: A Resolution of the City Commission authorizing a contract modification to Gavarrete Inc.’s Contract No. IFB 2024-031 pursuant to Section 2-764 of the Procurement Code entitled "Approval of Change Orders and Contract Modifications”, to allow for a contract modification in an amount estimated at $20,000 or not to exceed the available budget, for the Parking Lot 8 and 17 Improvements project. Lobbyist: N/A
Attachments: 1. R-2025-368 - Signed, 2. _AGENDA ITEM Agenda Cover Memo - Parking Lots 8 and 17 Improvements, 3. _AGENDA ITEM Resol - Parking Lots 8 and 17 Improvements

Title

A Resolution of the City Commission authorizing a contract modification to Gavarrete Inc.’s Contract No. IFB 2024-031 pursuant to Section 2-764 of the Procurement Code entitled "Approval of Change Orders and Contract Modifications”, to allow for a contract modification in an amount estimated at $20,000 or not to exceed the available budget, for the Parking Lot 8 and 17 Improvements project.

 

Lobbyist: N/A

Body

On November 8, 2024, Gavarrete Inc was awarded the contract for the Parking Lot 8 and 17 Improvements project through a competitive solicitation process issued as IFB 2024-031 in the amount of $667,790.

 

The project included the following scope of services: new landscaping, irrigation, lighting, EV charging station and resurfacing. The additional spending authority being requested will cover the installation of electrical equipment protection at both lots, as requested by the city inspector.

 

Under Section 2-764 of the Procurement Code entitled “Approval of Change Orders and Contract Modifications,” the spending authority shall be modified in the amount of $20,000, or an amount not to exceed available budget. This modification will provide the additional funds necessary to address the repairs to the asphalt joint required to complete the project.

Fiscal Impact

The installation of electrical equipment protection will help prevent future equipment damage and reduce the risk of personal injury.