File #: 07-0979    Version: 1 Name: UofM Basketball Fieldhouse sewer connection
Type: Resolution Status: Adopted
File created: 10/17/2007 In control: City Commission
On agenda: 10/23/2007 Final action: 10/23/2007
Enactment date: Enactment #: 2007-240
Title: F.W. Zeke Guilford, P.A., on behalf of the University of Miami, Owner, for permission for an outside sewer connection to the City's pressure system to serve the University of Miami's Basketball Fieldhouse Practice Facility, located at 1245 Dauer Avenue, Coral Gables, Florida.
Attachments: 1. Corrected basketball cover.pdf, 2. Corrected Basketball Res.pdf
Title
F.W. Zeke Guilford, P.A., on behalf of the University of Miami, Owner, for permission for an outside sewer connection to the City's pressure system to serve the University of Miami's Basketball Fieldhouse Practice Facility, located at 1245 Dauer Avenue, Coral Gables, Florida.
CITY MANAGER'S RECOMMENDATION:
That a Resolution requesting an outside sewer connection to the City's pressure system to serve the University of Miami's Basketball Fieldhouse Practice Facility, located at 1245 Dauer Avenue, Coral Gables, Florida, be approved, subject to Public Works Department conditions.
BRIEF HISTORY:
As stated in Mr. Joe Folino's Letter of Agreement, the proposed Basketball Fieldhouse Practice Facility is an addition to the Bank United Center, located on the east side of the existing building, and will connect to the University's gravity sanitary system seventy-five feet (75') upstream of existing lift station No. 1. From this lift station the flow will ultimately connect to the eighteen inch (18") force main along Ponce de Leon Boulevard.

The recommendation is subject to the following Public Works Department conditions:

1. That the Owner executes an Agreement approved by the City Attorney, agreeing to comply with the terms outlined in Resolution Nos. 24481 and 27941.

2. That the Owner pays a connection fee concurrently upon signing the Agreement based on the estimated gallonage. The fee has been calculated at $45,480.00.

3. The property owner shall provide the City with final plans and specifications as prepared by a registered Civil Engineer, licensed to practice in the State of Florida and fully experienced and qualified in the design of sanitary sewer systems for approval by the City.

4. That an Agreement be executed between the University of Miami and the City, before service is provided (the Applicant is responsible to attain and achieve the agreement with all the participants involved).

5. The property owner shall provide Liabili...