City of Coral Gables

File #: 24-7769    Version: 1 Name: 4231 SW 16 St Outside Sewer Connection
Type: Resolution Status: Adopted
File created: 7/3/2024 In control: City Commission
On agenda: 7/9/2024 Final action: 7/9/2024
Enactment date: 7/9/2024 Enactment #: 2024-150
Title: A resolution authorizing the execution of an agreement for sewer connection for property located outside the City’s sewer district at 4321 SW 16 Street, Miami, Florida into the City of Coral Gables wastewater collection / transmission system, subject to the requirements of the Public Works Department, as provided under Chapters 62 and 78 of the City Code, Ordinance Nos. 2007-29 and 2009-39 and Resolution No. 2008-07; and provided that the executed agreement be made part of this resolution.
Attachments: 1. R-2024-150 - Signed, 2. 4231 SW 16 St -Outside Sewer Connection- COVER, 3. 4231 SW 16 St -Outside Sewer Connection- RESOL, 4. Letter of Agreement, 5. City Code 78-106, 6. Ordinance No. 2007-29, 7. Ordinance No. 2009-39, 8. Resolution No. 2008-07
Title

A resolution authorizing the execution of an agreement for sewer connection for property located outside the City’s sewer district at 4321 SW 16 Street, Miami, Florida into the City of Coral Gables wastewater collection / transmission system, subject to the requirements of the Public Works Department, as provided under Chapters 62 and 78 of the City Code, Ordinance Nos. 2007-29 and 2009-39 and Resolution No. 2008-07; and provided that the executed agreement be made part of this resolution.

Body

Property Owners, Timonthy Riera-Gomez and Kayla Riera-Gomez are requesting authorization for an outside sewer connection into the City’s sanitary sewer district.  The property is located at 4321 SW 16 Street and shall be subject to the requirements of the Public Work Department, as set forth in Chapter 62 and 78 of the City Code, Ordinance No. 2007-29, and No. 2009-39 and Resolution No. 2008-07.

The property will be connected into the City 3 basin service area discharging into Miami-Dade Water and Sewer Department.  As per Miami-Dade Department of Regulatory and Economic Resources (RER), the receiving pump station has sufficient capacity for the proposed project and all downstream pump stations, including the treatment plant, have capacity, at this time.

The property Owner agrees to comply with the terms outlined in Ordinance Nos. 2007-29 and 2009-39 (City Code Section 78-106), and Resolution No. 2008-07 and enter into an agreement, according to Mrs. Riera Rodriguez’s Letter of Agreement to be approved by the City Attorney’s Office.

Concurrently, upon signing the agreement, the property Owner agrees to pay the City of Coral Gables a connection fee based on the estimated daily peak flow.  The estimated daily peak flow was estimated based on the proposed additional average flows of 310 GPD with a peak factor demand of 4.45. For an estimated peak flow demand of 1,380 GPD. The fee has been estimated to be $2,898.

The property Owner shall provide a Mainte...

Click here for full text