City of Coral Gables

File #: 16-4705    Version: 1 Name: MM-Giralda streetscape GMP Ric-Man
Type: Resolution Status: Adopted
File created: 1/14/2016 In control: City Commission
On agenda: 1/26/2016 Final action: 1/26/2016
Enactment date: 1/26/2016 Enactment #: 2016-33
Title: A Resolution approving a contract for the construction of the Miracle Mile and Giralda Avenue Streetscape Project (the Project) with Ric-Man International, Inc. for a guaranteed maximum price (GMP) of $21,600,000; providing for amendments as approved by the City Manager and City Attorney prior to final approval; further waiving the Procurement Code pursuant to Section 2-583, entitled “Application of the Code,” to authorize the City Manager to direct purchase certain items as specified in the Plan Design Specifications for the Project, and included within the GMP, as follows: stone pavers, stone furniture, lighting, and trees; further approving the direct purchase of additional pavers not included in the GMP for a price not to exceed $300,000 to be available for future uses for the Project; further authorizing the City Manager to execute a contract with Cooper Robertson and Associates in an amount not to exceed $500,000 to provide Construction Administration Services for the Project; fu...
Attachments: 1. Signed Resolution 2016-33, 2. CM Miracle Mile GMP, 3. Miracle Mile GMP RESOL, 4. public outreach, 5. GMP Contract, 6. Verbatim Transcript - CCMtg January 26 2016 - Agenda Item H-4 - Resolution approving a contract for the construction of the Miracle Mile and Giralda Avenue Streetscape P

Title

A Resolution approving a contract for the construction of the Miracle Mile and Giralda Avenue Streetscape Project (the Project) with Ric-Man International, Inc. for a guaranteed maximum price (GMP) of $21,600,000; providing for amendments as approved by the City Manager and City Attorney prior to final approval; further waiving the Procurement Code pursuant to Section 2-583, entitled “Application of the Code,” to authorize the City Manager to direct purchase certain items as specified in the Plan Design Specifications for the Project, and included within the GMP, as follows: stone pavers, stone furniture, lighting, and trees; further approving the direct purchase of additional pavers not included in the GMP for a price not to exceed $300,000 to be available for future uses for the Project; further authorizing the City Manager to execute a contract with Cooper Robertson and Associates in an amount not to exceed $500,000 to provide Construction Administration Services for the Project; further approving the Project budget; and the waiver of City fees for the project.

Body

The Miracle Mile/Giralda Avenue project is the result of decades of Community visioning. The project includes the transformation of the public realm to create a civic promenade that will become a focal point for the region. When completed Miracle Mile will include a beautiful, curbless, granite paver pedestrian environment nearly 50% wider than it is today. This new environment will include extensive landscaping and trees, sidewalk cafes, public art, beautiful lighting, comfortable and inviting street furnishings and enhanced drainage. Additionally, Giralda Avenue will be a spectacular shared pedestrian environment that includes creative and artful paving, lighting, and landscaping. It is anticipated that Miracle Mile and Giralda Avenue will be streets that are world renowned, and a “must place to be.”

 

In December 2014, the City Commission approved the award of a design contract to Cooper Robertson for the Miracle Mile/Giralda Avenue Streetscape project and in April 2015 the City Commission approved the selection of Ric-Man International, Inc. as the  Construction Manager at Risk contractor for the project and on August 27th, 2015 approved A Resolution authorizing the City Manager to begin negotiations with Ric-Man International, Inc. for a Guaranteed Maximum Price (GMP)  for the construction of the Miracle Mile and Giralda Avenue Streetscape project.

 

The final design of the project represents a collaborative effort by the Community encompassing more than 28 public meetings, including the dedicated and tireless efforts of the Steering Committee members who participated in nine design workshops and countless other meetings; review and input by City Boards and Commissions, the Community at large, and the guidance and direction of the City Commission as shown in attachment “A”, Public Outreach.

 

Over the past several months, the project team including Cooper Robertson and Partners, Ric-Man International, Inc., AECOM and Stantec as agents for the City, and staff have collaboratively worked together to refine the project plans to improve value and constructability while assuring that the community’s vision for the project is maintained. This effort has successfully resulted in the attached proposed contract with Ric-Man International, Inc. The following recommendations for modifications and adjustments to the plan include;

                     Improved and enhanced drainage system

                     Substitution of traditional Coral Gables Beige concrete in lieu of shell concrete at corners and tree wells

                     Traditional irrigation system

 

The project budget is as follows:

(Project Budget)

 

 

 

 

 

 

Giralda

Miracle Mile

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Design

 

 

 

 

 

 

 $            450,000

 $                  1,850,000

 

 

 

 Giralda Design:

 $            450,000

 

 

 

 

 Miracle Mile Design:

 

 $                  1,850,000

 

 

 

Design Subtotal:

 

 

 

 $                   2,300,000

 

Ric-Man Construction GMP Contract

 

 

 

 

 

 

 $         3,900,000

 $                17,600,000

 

 

 

CCTV Conduit

 

 $                     100,000

 

 

 

 Giralda GMP:

 $         3,900,000

 

 

 

 

 Miracle Mile GMP:

 

 $                17,700,000

 

 

 

Ric-Man Construction GMP Contract  Subtotal:

 

 

$                  21,600,000

 

 

Construction

 

 

 

 

 

Construction administration

 $            100,000

 $                     400,000

 

 

 

Construction inspection & testing

 $              80,000

 $                     270,000

 

 

 

 Giralda Construction:

 $            180,000

 

 

 

 

 Miracle Mile Construction:

 

 $                     670,000

 

 

 

Construction Subtotal:

 

 

 

 $                      850,000

 

Additional

 

 

 

 

 

Additional paving materials for storefronts$50,000

 $                     250,000

                            

 

 

 

Moveable furniture

 

 $                       60,000

 

 

 

Miscellaneous project costs

 $            250,000

 $                     750,000

 

 

 

 Giralda Additional:

 $            300,000

 

 

 

 

 Miracle Mile Additional:

                                     $                     1,060,000

 

 

 

 

Additional Subtotal:

 

 

 

 $                      1,360,000

 

 

 

 

 

 

 

 Giralda  Total:

 

 

 

 $                4,830,000

 

 Miracle Mile Total:

 

 

 

 $              21,280,000

 

Project Grand Total:

 

 

 

 $             26,110,000